

The facility features an activated sludge process system. Additionally, the facility is equipped with an emergency standby diesel generator.
Identified as a top priority during the development of the District’s Parks Master Plan, this portion of trail was the first phase of over two miles of planned trails to provide connectivity and recreation for District residents.
EHRA conducted a traffic engineering study to identify the impacts of a proposed master development located near the intersection of FM 1488 and Peoples Road in the City of Conroe.
The purpose of this project was to convert the existing at-grade crossing of Brazoria County Road 56 (CR 56) and State Highway 288 (SH 288) into a diamond interchange that includes a new overpass bridge. Coordination with TXDOT, area landowners, utility companies, and Brazoria County was integral in obtaining approval and acceptance of the project.
EHRA completed preliminary engineering, phase one environmental site assessment and schematic development for the widening of Northpark Dr. between US 59 and Woodland Hills Dr. EHRA also provided program management, drainage analysis and design, traffic engineering, environmental documentation and schematic design for the roadway, as well as grade separation at the Loop 494/UPRR railroad crossing.
EHRA conducted traffic operations and access management studies for the Northpark Dr. corridor. This corridor is approximately 2.2 miles long and has major signalized and unsignalized intersections and driveways that access various subdivisions and industrial developments. These studies laid the groundwork for the widening of Northpark Dr. from a four-lane boulevard cross-section to a six-lane boulevard complete street. The new street design includes low impact development drainage, conventional drainage, a grade separation at the UPRR crossing with mechanically stabilized earth retaining walls, two at-grade crossings for bi-directional frontage access, reconstruction of two concrete bridges over a diversion channel, intersection improvements, a roadway-adjacent multiuse path and traffic signal improvements.
Drainage analysis and design included hydrologic and hydraulic studies of both existing and proposed conditions to demonstrate that proposed project components would not adversely affect the 100-year floodplain in the area. The roadway and traffic designs contained horizontal and vertical alignments, cross-sections, plan and profile, sidewalk and bicycle accommodations, intersection layouts, traffic control plans and signing and pavement markings.
As the program management firm, EHRA coordinated with TxDOT, UPRR, the City of Houston Council District E, COH Planning and Development Department, COH Public Works and Engineering Department, Montgomery County, Harris County, HCFCD and area residents throughout the project.
Fort Bend County Engineer Grady Mapes gave updates on several major countywide construction projects at a Texas Department of Transportation Business Roundtable presentation Friday morning at the Rosenberg Civic Center. Check out the list below for the latest on these major road projects.
The $156 million project that runs along I-69 from the Grand Parkway to Reading Road began in 2014 and is set for completion by early 2019. Here are three key updates within the project:
Williams Way was closed on June 2. Traffic was switched up onto the new I-69 bridge on June 18. Currently, a Williams Way intersection is being built underneath I-69, and Williams Way will be reopened Aug. 2
A new southbound frontage road will be used to shift traffic to FM 762. The remaining pavement where the existing FM 762 exit traffic is in the process of being completed and a new dedicated exit lane will be added.
Construction on an overpass at Reading Road is scheduled to begin in February 2018 and be completed by May 2018. The project will redirect Reading Road down off I-69 to become an at-grade intersection. Construction will not start until early next year due to holiday shopping that is expected at nearby town shopping centers.
An elevated intersection at Hwy. 90A and FM 359 will form over the Union Pacific Railroad tracks. The $24.5 million project began in June 2016 and is scheduled for completion in May 2019.
This $18.4 million project consists of constructing an overpass over the BNSF railroad tracks at the Richmond/Rosenberg city limits. The project will begin in late 2017 and is scheduled to be complete within 36 months. The project has been put on hold because construction crews are waiting on confirmation from AT&T personnel.
This $4.5 million project runs from Frost to Millie streets and started construction late last year. Construction crews have plans to open the crossover between Damon and Louise streets next week, but that date is tentative. Traffic now runs four lanes each direction.
This project is awaiting work authorization and includes constructing a bridge over the railroad tracks on Hwy. 90A and Hwy. 36. The project cost is $25 million and has a scheduled duration of 27 months. There are two existing railroad passes under Hwy. 90A and Hwy. 36, and when the project is completed overpasses will be constructed over the railroad tracks. The area around Hwy. 36 is prone to flooding; because of this, the project was delayed and will not start until the fall.
This project runs from Hwy. 59 to SH 36 and is still in the design phase. It is not scheduled to go to bid until fall 2018. The project is estimated to cost $36 million and take three years to complete. The widening will include changing the roadways from asphalt to concrete.
This project is still in the design phase and consists of two different segments that will run from north of FM 2218 to the Fort Bend/Brazoria County line.
This project involves the reconstruction of I-10 from Brookshire to the Brazos River. Currently, I-10 consists of two lanes that run in each direction. Widening I-10 to three lanes will help with congestion that typically forms at the start and end of the weekend for people traveling to San Antonio.
Mapes said lane closures are inevitable but once the project is done, three lanes will run along I-10 to San Antonio. TxDOT’s Houston District will be responsible for the project up until Columbus, and the San Antonio District will take on the project from Columbus to San Antonio.
(Source: Community Impact News)