

EHRA designed an expansion that implemented the installation of a new triplex lift station operating in conjunction with the existing duplex lift station.
Facilities requiring expansion were also common wall construction, and the EHRA team converted the facilities into aerobic digesters and sludge thickeners.
Engineering design and construction phase services of water, sewer, drainage and paving for four subdivision sections and off-site channel (123 acres out of a 400 acre subdivision). There was 60-feet of elevation difference on this site and wooded lots were left in their natural state which required the installation of retaining walls.
EHRA worked with the District to create a comprehensive Parks Master Plan, which included recommendations for the development of over two miles of hike/bike trails adjacent to local streets, and within flood control and utility pipeline easements. The District began implementation of the Plan by prioritizing the beautification of West Road, a major arterial street that runs through the District.
EHRA assisted with the district creation of Montgomery County Municipal Utility District No. 126 to accommodate a ±329 acre master planned community located in northern Montgomery County in the City of Conroe, south of League Line Road, west of Longmire Road, and adjacent to Lake Conroe.
EHRA Engineering was contracted by Dang La to help develop approximately 21 acres of land, known as Marketplace 249, for a mixed use commercial development. EHRA consulted Dang La on different approaches to developing the tract in which they were able to save money as well as get reimbursed for the detention basin which served multiple users of the 21-acre tract. The tract is maintained and owned by Northwest Park Municipal Utility District (MUD). The EHRA Hydrology and Hydraulics team, led by Andy Palermo, PE, CFM, executed a drainage needs and impact analysis for the Marketplace 249 project. Soon after, the EHRA Site Development team, led by Matt Gutzwiller, PE, joined in the professional services efforts and began site work for the project.
The site design included components such as public utility extensions, regional detention/mitigation basin, paving, stormwater design and water and sanitary solutions for areas up to five feet from the multiple buildings. Throughout the execution of these project elements, one major objective for the site team was to ensure a timely and seamless execution of the project. In order to deliver on this request, EHRA developed the public infrastructure (regional detention and public utilities) with the private site utility design preliminarily laid out. This allowed for a seamless private site design tying to public infrastructure utilities.
Site Development Project Manager, Matt Gutzwiller, PE, shares that the best part about working on this project was the forward thinking and creative design ideas that EHRA utilized. For example, ensuring adequate driveway ties were provided with increased subgrade to ensure seamless connections by future landowners with reduced potential for damage to the existing roadway. EHRA made certain to incorporate ample utility stub outs for potential pad sites (beyond the current scope), considering the initial site layouts shared with Dang La.
One particular challenge the Site Development team faced was that the existing sanitary was shallow and ensuring all buildings have adequate sanitary depth at the building tie-in location. This was achieved by increasing some of the pipe sizes to reduce the slope, as well as strategically running the sanitary sewer through the site.
Marketplace 249 is still under construction, with 2 buildings and 1 pad site remaining to be built out. Additionally, there is a forthcoming phase spanning approximately 12 acres, awaiting development, along with plans to expand the regional pond to accommodate the future phase. EHRA takes pride in contributing to the realization of Dang La's vision, aimed at introducing a contemporary shopping center for the benefit of local residents and employees. This initiative has not only elevated the area's value but also set the stage for prospective growth.