EHRA conducted a traffic engineering study to identify the impacts of a proposed master development located near the intersection of FM 1488 and Peoples Road in the City of Conroe.
A 720-acre gated master planned community located off Telge Road, just north of Willow Creek. See how EHRA was involved in this project.
The new roadway design comprises of one-half major thoroughfare, conventional drainage, a 600-ft long bridge over Willow Fork Bayou, Retaining walls and intersection improvements at FM 1463 (including traffic signals and illumination).
EHRA was selected as one of two firms to provide professional surveying services under contract to Houston Community College System.
EHRA completed preliminary engineering, phase one environmental site assessment and schematic development for the widening of Northpark Dr. between US 59 and Woodland Hills Dr. EHRA also provided program management, drainage analysis and design, traffic engineering, environmental documentation and schematic design for the roadway, as well as grade separation at the Loop 494/UPRR railroad crossing.
EHRA conducted traffic operations and access management studies for the Northpark Dr. corridor. This corridor is approximately 2.2 miles long and has major signalized and unsignalized intersections and driveways that access various subdivisions and industrial developments. These studies laid the groundwork for the widening of Northpark Dr. from a four-lane boulevard cross-section to a six-lane boulevard complete street. The new street design includes low impact development drainage, conventional drainage, a grade separation at the UPRR crossing with mechanically stabilized earth retaining walls, two at-grade crossings for bi-directional frontage access, reconstruction of two concrete bridges over a diversion channel, intersection improvements, a roadway-adjacent multiuse path and traffic signal improvements.
Drainage analysis and design included hydrologic and hydraulic studies of both existing and proposed conditions to demonstrate that proposed project components would not adversely affect the 100-year floodplain in the area. The roadway and traffic designs contained horizontal and vertical alignments, cross-sections, plan and profile, sidewalk and bicycle accommodations, intersection layouts, traffic control plans and signing and pavement markings.
As the program management firm, EHRA coordinated with TxDOT, UPRR, the City of Houston Council District E, COH Planning and Development Department, COH Public Works and Engineering Department, Montgomery County, Harris County, HCFCD and area residents throughout the project.
Construction Costs Continue to Decline Heading into 2027!
In our June 2026 Construction Cost Trends update, we shared encouraging news about declining infrastructure construction costs across the Greater Houston region. As we approach the end of 2026, updated construction bid results collected by EHRA's Construction Services team indicate that this favorable pricing trend is continuing.
All four of our key construction cost indicators are approaching levels comparable to those seen in 2021. Underground utility construction costs have declined approximately 28% to 31% from their respective peak trendline levels, while concrete paving costs have decreased approximately 13%.
These continued improvements are welcome news for developers, municipalities and utility districts as they evaluate project budgets, advance capital improvement programs and prepare for new development opportunities in 2027.
In the charts below, we highlight the latest pricing trends for four key construction cost indicators that serve as benchmarks for public infrastructure and land development projects.
Let's take a closer look at the numbers.
8" PVC Water Main construction costs continue to trend downward, with recent bid prices coming in well below the elevated levels experienced in previous years. Overall trendline pricing has declined approximately 30% from its peak in late 2023, with many recent bids ranging between $30 and $37 per linear foot. Current pricing is approaching levels last seen in 2021.

8" PVC Sanitary Sewer construction costs have followed a similar downward trajectory, with pricing continuing to soften throughout 2025 and 2026. Overall trendline pricing has declined approximately 28% from its peak in early 2023. With most recent bids ranging between $33 and $43 per linear foot, sanitary sewer construction is showing considerable improvement in both cost and pricing consistency.

24" RCP Storm Sewer construction costs have experienced the most significant percentage reduction among our four key construction cost indicators. Since reaching peak trendline pricing in early 2024, costs have declined approximately 31%, with many recent bids ranging between $60 and $80 per linear foot. Although some variability in bid pricing remains, the continued downward trend is encouraging news for upcoming infrastructure and land development projects.

6" Concrete Paving costs continue to show a gradual decline, with overall trendline pricing down approximately 13% from its peak in mid-2023. Most recent bids are ranging between $45 and $55 per square yard. While the reduction has been less dramatic than those seen in underground utility construction, the continued improvement in paving costs further contributes to a favorable construction market.

As we look ahead to 2027, the continued decline in infrastructure construction costs presents encouraging opportunities for the Greater Houston land development community. While market conditions can change, current pricing trends indicate a favorable environment for moving projects forward.
EHRA's Construction Services team will continue monitoring construction pricing across the region and sharing valuable market insights to help our clients make informed decisions about project planning, budgeting and construction.